What are the phases of the construction process?

Step 1: Make Ready Engineering

Examine existing infrastructure and create design sheets. Timeline: 18 weeks.

Step 2: Make Construction Ready

Make plans to get existing infrastructure ready for adding fiber lines. Timeline: 18 weeks.

Step 3: Construction

Bury fiber cable underground and string it from poles to build the network that connects homes to our fiber hut. Timeline: up to 14 weeks.

Step 4: Splicing

Splice the necessary cables at each end point and mount splices in enclosures secured to distribution poles. Timeline: up to 14 weeks.

Step 5: Service Drop

Extend the fiber cable from the nearest splice point to the area receiving service. Timeline: approximately 6 weeks.

Step 6: Installation

Once the fiber network is ready, the team will hook up homes and businesses to receive high-speed internet service.

Visit our C2F Construction Process page for more information.

What Is Fiber-Optic Internet?
  • Fiber internet sends data on pulses of light instead of pulses of electricity. This method of transmitting data is much faster and can go farther than cable and DSL connections. It is also immune to electromagnetic interference that other connections are susceptible to. With Connect2First, 100% of our fiber cables are connected directly to the home. No matter where you live, homes and businesses will have direct access to the fastest internet available.
  • In today’s world, a lack of connectivity negatively impacts education, commerce, community growth, healthcare and quality of life. We’re proud to launch Connect2First and bring some of the fastest internet speeds available. Our services will drive innovation and economic development to the communities that need it most.